How do we calculate the building footing calculation ?
Answer Posted / ds raju
Question is not clear. Is it design calculation ? or RCC
volume of the footing.
Design calculation depends on the safe bearing cpacity of
the soils and load on the footing.
Concrete volume can be calculated based on the shape of of
the footing.
For Rectangular/ square type : LxBxH
For Trepezoidal type : h/3 (Area at bottom-A1 + Area at top-
A2 +SqRt of (A1xA2)
| Is This Answer Correct ? | 36 Yes | 2 No |
Post New Answer View All Answers
beam length 73 feet 4 inch,width 01 feet,height 50 inch so every beam load how much? and what quantity of M.S ROD? both side ony two column in middle no column.pls inform me that this is stable or not ? and how much risk of this beam?
100mm block work 64 bags of cement used 150mm block work 286 bags of cement used 200mm block work 20 bags of cement used patly work (M15) 293 bags of cement used mortar ratio is 1:5 how to calculate volume of sand in cum & no. of bags
how many minimum admixtures are used in water froofing structures
How to calculate laplength for 3 floors
Design a cantilever type retaining wall to retain sand for 4m above the ground. The sand fall slopes at the rate of 1 vertical to 2 horizontal. The weight of sand is 18000 N/m3, the angle of repose being 30. The safe bearing capacity of the soil is 200 kn/m2 at 1/25m below the ground level. Use m 15 concrete mix.
how to take the quantity of block work and plastering 1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate
how can we calculate steel value, depending on load
Before casting a basement roof slab which is connected with retaining wall surcharge load (i.e. sand or earth filling) outside the retaining wall is prohibited because of––
What are the benefits of rcc pipes over steel designed pipes?
How to calculate the weight of sand am 20mm course aggregate in 1 c.m M25 concrete Which use 400 kg of cement ?
(Project Management Topic) What are the important criteria in the successful realization of the project?
All aptitude question of Bechtel
What are the joints wants to made in masonry where door opening, arches like etc..
for pretensioning which will yield first and same for post tensioning?
How to calculate concrete in percentage wise ,for example cement 18% sand 40% aggregate 40% and Stell 2% ,I need and??