If i have two 3000 kW motors and the whole facility requires
a 10 MVA transformer.
What would be better installing two 5 MVA transformers(one
for 1 motor ) or just a single 10 MVA transformer for both
of them.
Give reasons for your answer.
Answer Posted / k.prakashchandra
It is better to have 2x5 MVA.If one of them fails or
maintenance work is to be taken up ,you can use one of the
motors.
| Is This Answer Correct ? | 1 Yes | 2 No |
Post New Answer View All Answers
what are the stresses in circuit breakers ?
How to calculate capacitor bank value to maintain unity power factor with some suitable example?
magnetizer priciple
Hi, Next week Iam appearing RRB exam for section engineer. So help me to get modal question papers for this position. Iam very thankful to you. Whether question will be fully techanical format or general form. Please give me a details regarding this exam.
explanation of mesh bus bars
Define branch?
How can we connect additional batteries to three phase ups? What are parameters we have to check when connecting?
in india per day how much power is generated including all power station
Why does the rotor rotate?
How can we calculate the motor frame sizes?
all the technical question with answers pleas send your email id ramar_eee@yahoo.com
i have 500 amp inductive load of motors ,,,pleas tell me how can i calculate for capacitor bank for improving my power factor to 99 .....calcullations for capacitor bank,,,,
What are safety device in vcb and acb?
what is the use of permanent magnet generator in exciter
Write the programming software name for LG, SIEMENS,Messung,AB