Answer Posted / k.prakashchandra
Your setting is 15% of In.While charging ,Tr draws initial
magnetizing current 6 to 15 times the In. Any difference in
measurements by CT s at this current ,may exceed the set
current.Even 1% error in measurement at normal current
becomes 15% of In at initial charging current at 15 times
the In
| Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
Witch do depand of Power factor and theory of power factor?
to vary valtage from 0 - max a variac is necessary . so how to design for high power applications nearly about 200KW power
10 Mtr Hight of Lighting Arrestar how much area coverd??
Draw a SLD of HT distribution EB grid up to users Transformer?
A 3-phase IM is supplied from 50 Hz system. It runs at speed of 1440 rpm and slip equal to 4 %. Calculate number of pole pairs. A 1 B 6 C 2 D 3
ROC converges if poles and zeros lie inside a. Origion b. Z=1
What are the different types of transformers?
I'm looking for a softcopy manual set for a Credence ASL- 3000. Anyone know where I can get it?
How could I get a certificate of competency as Electrical Supervisor? I have completed By BTech in Electrical this year(2012) for VJTI Mumbai Maharashtra. Is it compulsory to be produced while joining?
Purpose of providing neutral isolation panel for parallel operation of diesel generator
I am applying for NTPC examination.Can we please provide previous paper to my mail prasad.chintala108340@gmail.com
please send me previose rrb junior engineer qustion papers
what are safety measures in /control in diesal engine/ explain them?
I need to connect a synchronous generator to the grid using automatic synchronization and two circuit breakers (one for synchronization, one for end connection to the grid), how to determinate the required diameter of the cables?
What is the effect of positive feedback on stability of the system?