Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How do we calculate the building footing calculation ?

Answer Posted / guest




Dear friends generally we do this footing calculation like
this two method =
(A)1st method =i)1.500 m x 1.500 m x 0.500 m = 1.13 Cum.
ii)½ x ( 1.500 m + 0.250 m ) x 1.500 m x 0.200 m = 0.260
Cum. (B)2nd Method =i)(1.500 x 1.500 x 0.200)+ (0.250 x
0.250 x.0.250)= 0.460 Cum.
ii) ( 1.500 x 1.500)+ ( 0.250 x 0.250)/2 x 0.200 = 0.231
Cum.
( But I think it is not proper procedure so please you do
properly )

Is This Answer Correct ?    10 Yes 33 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

we have a crushing plant and our product is experiencing flakiness and elongation over limit for granite. what is the solution to this problem? how can it be avoided and what to do differently? It is not ok for batching plants

2127


How to Know that veriation acceptable in CPWD Work Of 1:6 Cement Mortor Received Lab test report.

2266


what is the hanekom repairing material after concreting work

2341


Define current ucs?

1365


i need the syllabus for the direcr recruitement of executive engineers in andhrapradesh

2339


What is the exception critarea of cube?

2479


what is the most suitable foundation when construct a bird watching tower in a marshy land

1806


Please tell me any one, how many quantity concrete paver block fixing perday ( 8hours) per mason??

1625


I want to change job.If You have any vacancy please contact me in this mail id-parthamitra086@gmail.com.Myself partha mitra.Diploma in civil engineer with 4+ yrs. exp.Now in kolkata.If you confirm me then I will send my detail resume to you.Also send your mail id to me.My mail id is-parthamitra086@gmail.com.I will be very much thankful to you.

2046


percentage of metal,clay or soil & water in water bond macadam roads to know the quantities for each in total volume of 11500 cubic meters

2098


In a concrete grade C35A, C & A stands for what and equalent cube strength?

3595


how much repeitation for conventional and maivan formwork?

1981


What do we mean by partial moment release ??

3815


How can we calculate 8- storied Madrasha Building pile capacity by taking SPT value at site?

2003


Re: Can anybody help me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates? please my email id is smgujjal@gmail.com

1959