we callculat main steam flow by D.P. but where is H.P. &
L.P. IN Orfics?
Answer Posted / fareed
H.P.is the upstream side & L.P.is the downstream side of
the line
| Is This Answer Correct ? | 11 Yes | 2 No |
Post New Answer View All Answers
why we use cascade control and feed foreword control in 3 element control of boiler drum ?what is feed forward and cascade control system ?
Hi Friends i need Electronics&Instrumentation Engg question papers for BARC written test by coming 20th May 2008 pls post ur use full info to kkumarei@gmail.com. Or for suggestions pls give one missed call to 9962122264
explain key exchanges in all security modes WPA,WPA2,TLS?
How it the difference between force balance system and dispalacement balance system?
find the kp ki kd from the transper function G(S)=29.44s+04707/1.5349s2+s
What is the purpose of bypass valve across AS valve.
Can anybody please let me know Orifice plate sizing calculation formula and step by step procedure
types of cable..? Use of every types of cable..?
Explain how thw analog to digital converter works with the circuit diagram
what is function of sensor, and how is it work , explain with difination
How r the calculation of process line mpm.
what are the different types of Protocols? & their applications.
For crude application in floating roof tank, how to calibrate a DP Transmitter? How is the floating roof weight considered?
Make Heater Process Logic.
Hi,can anyone help me out with PhD programs related to Instrumentation field?I have a degree in electronic Instrumentation?