Generally the thumb rule is
for 100 Cum of concreting 10MT of steel is required.
More over this varies with the type of construction like for light structures it varies from 8-10MT
Med Str 9-12MT
High strength Structures(Industrial) 10-14MT of steel is reqd.
| Is This Answer Correct ? | 16 Yes | 2 No |
Post New Answer View All Answers
How to find CN by using arcgis 9.3?
Dear Engineers, Can you please advise me the material requirement to construct a room 4 M x 4 M 1. No. of Standard Brick 2. Requirement of Cement Bags 3. And Concrete for Steel, Cement, sand, etc Thanks
How do you prepare Material Recovery Statement for deduction from contractors bills?
how much cost of single coat 20mm thick plastering per sqre meter
what are the cube & Sylinder strength of concret M20,M25,M30,M35,M40,M60 ,M75,M10 ,M15
what is Brick crushing strength(PSI)?
what is concrete canvas?
In the design of bridge arguments what considerations should be made to select the orientation of the wing walls?
What is difference between engineering stress and true stress?
do we decide reinforcement steel , based on bending moment ? give example with continous slab?
How to check slab shuttering level.? Or check list for slab ?
Define absolute co-ordinates?
Kindly post me previous year interview questions with answer for post of DY. Manager (civil engg.) for GAIL, NTPC, IOC, OIL and ONGC etc.
Calculation of Pier Cap with tapper area?
Is there any course for billing available in Mumbai? If yes then please mail me the details..