Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete
by explaining all formulas involved.
Answer Posted / s s grewal
Before calculating the quantity of concrete required for size of pillar or size of footing at (D=0.5 m)
Formula :- L X B X d + D-d/3 x A1 + A2 + √(A1 X A2)
| Is This Answer Correct ? | 22 Yes | 9 No |
Post New Answer View All Answers
Soil bearing capacity formula
How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 100 microns?
What is quantity of cement and sand required for 2000sqft of tiling?
What do you understand by “preset” during the installation process of bridge bearings?
How many hours should traffic be not allowed after completing wbm road or bst.and min how many hours should road rollers be used.
how to calculate the mortar for 10'*10' size room for both plastering and for masonry work?
how to calculate the strength of rebound hammer test reading in building construction ?
what is the specific gravity of rubble in plum concert
how to Concrete cubes testing curing time 7 days casting date 24.05.17 testing date ?
Describe a time when you anticipated potential problems and developed Preventive measures
why we can use dust in concrete insted of fly ash
.5Ast
hi, i am appearing in HPCL(CIVIL ENGG.)exam. plz send me placement paper of this exam if u are having
can we make bricks using m10 grade cement concrete and what would be the ratio of raw materials used and price per brick ?
HOW SOON CAN YOU TRAVEL DON TO ANY LOCATION POSTED U?