What happen if LV supply is fed to a HT motor?
Answer Posted / a v subba rao
We can connect HT motor with LT supply in no load with out
any problem for site testing. Only thing motor will not
start due it will not devalop sufficient torque,but if we
rotate the shaft at the starting motor will start rotating
at lower speed first and it will slowly increse to up to
rated speed if we can not remove the supply. This test has
to be done only idle motor.
| Is This Answer Correct ? | 12 Yes | 6 No |
Post New Answer View All Answers
How to distinguish whether MCB is DC or AC looking at it physically
WHY MOSTLY Rph IS USED FOR CONTROL CIRCUITS AUX. SUPPLY ?
234 MVA Generator 3 phase Short circuit current Values required? Gen set Rating-234 MVA, Gen Voltage-18kv, PF;0.8, Xdv:23.5 %, Transformer Rating-18/380KV, 680MVA,Yndd1 two winding, Step up TR, ZT:35.50 %,X/R 4.33 Gen CB Position, CB open ,Disconnected open, Generator Running Voltage 18 Kv, Bi mistakes generator side earth switch Closed during that time short circuit current level in 3 Phase required, and how to test on site 234MVA Generator Short circuit current,
how to measure earth resistance of a substation
what is meant by twilight switches 7 where its applicable ?
What is K-rated transformer? What is the use of it? What can be the size(pls provide calculation if possible) of K- factor transformer for 550kW,690V motor operating with drive (VFD)?
with 3 phase board on a 63 amp rcd is it ok to have 6 electrical showers 2 on each phase and what problems could happen
what is the significance of terminal voltage and phase sequence in the operation of paralleling of two generators?
Who are the manufacturer for Nitrogen based Fire Protectio/explosion prevention for Oil Filled Transformers? India and international both?
Explain the process of commutation in a dc machine.
Draw a block diagramof Three UPS systems connected in Parallel mode?
explanation of mesh bus bars
what is formula to cal cute earth pit numbers and size of earth strip used in earthing?
When calculating the speed of a rotor required for a particular frequency of synchronous generator we use the equation 60f/p Is this p is the number of pole pairs of rotor & do we consider the number of pole pairs in the stator is 1?
how can maintaince the acb contactor moveing and fixing kit