How can we calculate quantity of slab, beam @ column ?
Beam should be calculated by deducting slab thickness or
slab should be calculate in to in ?
Answer Posted / g.satyanarayana
Beam Qty = over All Depth of Beam x Length between Columns x
Width of Beam
Slab Qty = Length & Breadth to be considered from inner face
of Beam to inner face of beam and thickness of Slab
Column Qty = Over all height of Column including over all
beam Depth
Finally deduction of Steel Volume from the Total Qty So arrived.
| Is This Answer Correct ? | 16 Yes | 9 No |
Post New Answer View All Answers
Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?
Which Types Of Bricks ?
Stringer How many cm goes to landind
manhole chamber having height of 2300 mm and thickness of brickwork is 230 mm and dia of opening covering is 560 mm and bottom length vertical is 1500 mm (1:4) brick masonry and plaster 12 mm on both sides..how to estimate the no bricks used with mortar cement bags and sand for total chamber including plaster.
what is cross hair cursor?
Minimum and maximum size of the building components
HOW MUCH STEEL REQUIRED FOR SLAB OF AREA 23'3"*18.3"? FOR SLAB HOW MUCH DIAMETER BAR WILL USE?
Define What is passive earth pressure ?
How cracks in concrete can be avoided?
explain the rale of the government in the construction industry
the magnitude of the buoyant force can be determine by newtons law of viscosity archimidies principal principles of momemnt none
I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
what is the cost difference of a same structure when it is constructed with brick masonary and when it is constructed with block masonary and concrete as a frame structure????????????????????????
How high should the water tank be to provide a 60 psi at base of this water tower?
what is box type waterproofing and how it is exsiccated and what is the method of doing box type waterproofing