How can we calculate quantity of slab, beam @ column ?
Beam should be calculated by deducting slab thickness or
slab should be calculate in to in ?
Answer Posted / g.satyanarayana
Beam Qty = over All Depth of Beam x Length between Columns x
Width of Beam
Slab Qty = Length & Breadth to be considered from inner face
of Beam to inner face of beam and thickness of Slab
Column Qty = Over all height of Column including over all
beam Depth
Finally deduction of Steel Volume from the Total Qty So arrived.
| Is This Answer Correct ? | 16 Yes | 9 No |
Post New Answer View All Answers
What is the Roll of Water Bonding under VDF road?
Design an underground tank of internal dimensions 6m x 3m x 3m. The soil surrounding the tank always remains dry. The tank shall be provided with a roof slab. The soil weighs 16000 N/m3 having an angle of repose of 30.
Describe the role of independent Quantity surveyor?
1m square 20mm plastering how much of water need curing work
How is calculate the cube molt
specifications of fe500 steel
what motivates you to do a good job
2. In a container filled with each of the following materials, at a porosity of 40%, determine the upward gradient required to cause the quick condition (a) Lead shot with a G = 13.75; (b) Fibre beads with G = 2.15; (c) Sand with a G = 2.32
03. a. The water cement ratio for achieving maximum strength of concrete is…… 1 b. Water/ cement is inversely proportional to-------------- 1 c. Increasing the slump decreases the strength: True / false 1
Coverage of 25mm.thick ratio of 1:4 cement mortar?
How much Tolerance factors like 1. brick work 2.plaster 3.painting 4.floor tiling 5.wall tiling 6.shuttering 7.concreting 8.steel
Suppose a new brick wall is being constructed,and the courses and not aligned horizontally,what negetives can it cause?
How much cements bag (or in KG) required for 1 Sq. M concrete, for M-30 grad concrete as per CPWD and where is thr proof on site
What is the cost of formwork for columns/beams/rcc walls also what is the cost of shuttering for roof slab at height of 25 feet
when reinforcement binding completed if there is more cover than the required what is the solution to reduce the cover?