1. why more stirrups are provided near the support?
2.where more stirrups is provided in a column and why?
3.why extra bars are provided at the top of beam?
4.what is the difference between overlap and lap lenght?
5.what is development lenght
Answer Posted / anurag mishra
1-To couteract the maximum shear stress developped at support
2-the Maximum shear stress zone in a column exists at the distance of l/3 from junctons of column with beam / slab ,so in this zone more stirrups are required to be provided,
3-at the ends of the beams, maximum hogging moment zone exists which causes column for faliure at top layer. this is why extra bars at the ends/ junctions of beams ,in top layer are provided.
4-o/lap length is the length of bar which is provided in the rienforcement where two bars are jointed linearly
lap length is the minimum specified length required for overlapping of two bars. its length is fixed for various grades of concretes.
5-The minimum length of bar required for the development of perfect bonding with concrete at the ends is called development length .it is calculated by Qst/4.tou.b.d
| Is This Answer Correct ? | 39 Yes | 5 No |
Post New Answer View All Answers
What is oneside mat. And explain
How do you calculate the power of a centrifugal pump?
water leak detection system question & answer
what is castigliano theaorem
Why should pumping be not used in case of concreting works?
What is thumb rule in quantity and cost estimation of a residential building in civil engineering??
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.
length where bent up is made in slab of bridge from one end
What is meant by dimensioning?
will fix foundation bolts at site with out template is there any procedure?
What is hybrid foundation?
residential projects,structural.
5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)
With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr
how to tie 10 legged stirrups