in our transmisison sub station why we step down firstly
132kv\33kv then 33kv to 11kv. can we direct step down 132kv
to 11kv.
Answer Posted / sudhir a kadam
usually this is done looking into the practical
requirements and availability of the transmission line. It
is not at all necessary that the HV 132 should be stepped
down to 33 KV. It can very well be directly stepped down to
11 KV. If we have a dual reqmt of 33 as well as 11KV.
132/33/11KV( pri/sec/ter) can also be designed.
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
What is a diode?
placing earthing pit in pathway is correct or wrong??. placing earthing wireGI1/18 inside walls is correct or wrong?. explain!!!
explain PV modules in solar energy generation.
how we arrange the hv side with delta connection in case 33/11kv of transformer.
I have 1500/1A CT If i connect this CT in 6.6KV bus bar means what will be the voltage present in CT?
How to select a contactor? How many types of contactors are available
What is ST and specify its range of voltage.
In an ACB shunt trip coil and undervoltage coil operated normally( breaker open and charged). But closing coil not operating untill manually discharge and recharging. Any help.
Does outdoor isolator loose connection cause short circuit current in that circuit? if yes then how ??
How do you determine the size of transformer radiators in a transformer?
how oltc works in rectiformers of higher rating (27 mva,200v dc,120kamps) please provide me full information with diaggram.
I need the recommended size for a 3 phase transformer at 13.8 KV Primary and connected loads of 3000 kVA at 4200 volts and 2375 kVA @ 480 volts AC.
In Designing the rating & accessories of a MCCB how to choose the type of releases..means what is the basis for selecting, thermal magnetic, electromagnetic & microprocessr based releases
What are motor generator sets and explain the different ways the motor generator set can be used ?
How to calculate cable size by using load.?? Any formula...