How much wastage we considered for cement
Answer Posted / praman srivastava
the wastage for steel & cement for mainly consider for
handling , tranpotation & workmanship & in case of steel
wastage consider for cutting bending & scrap during
work.Approximate 3% wastage consider for above as per CPWD
Norm.
| Is This Answer Correct ? | 44 Yes | 10 No |
Post New Answer View All Answers
What you understand by richter scale?
how to design and calculate materail quantity for concrete speedbreaker ?
what do you know that m20,m25
how much to get of BRC lapping in full yield and half yield ?
What is meant by engineering drawing?
what is diversion?
What is the origin of name railway sleepers?
Explain the term 'Gross unit rate' and identify the items that may be included in the gross unit rate.
What is the development length given in pile?
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
if the nitrates more than 45mg/l in water lead to disease then what is it called
can you give me the details of rate analysis of steel and concrete?
in the earthquqke the profile of water on dam is parabolic or not
Define What materials were used to build the Golden Gate Bridge?
HOW MUCH STEEL REQUIRED FOR SLAB OF AREA 23'3"*18.3"? FOR SLAB HOW MUCH DIAMETER BAR WILL USE?