How much wastage we considered for cement
Answer Posted / praman srivastava
the wastage for steel & cement for mainly consider for
handling , tranpotation & workmanship & in case of steel
wastage consider for cutting bending & scrap during
work.Approximate 3% wastage consider for above as per CPWD
Norm.
Is This Answer Correct ? | 44 Yes | 10 No |
Post New Answer View All Answers
What is the biggest dam in america?
If we are providing concrete joint in every 10m with water stopper in water tank wall then is it necessary to cut the steel at joint section?
How to build the floor to ceiling bookcase?
sir tell me the formula for calculating the volume of 380mm dia double under reamed pile of 4.0 mts depth.
What are the different approaches in designing the floors of the service reservoirs?
VAT and CST ? Which benefits for buyer ? Why benefits?
How is the strength of cement measured?
Why we provide hair pin for shed
what is raft foundation
How to marking the building
Pls help me to arrive the rates for centering shuttering for highbay using H-frames?
How much cum. Brick work can do by 1 madon
Define What is passive earth pressure ?
How to construct a water sump in a rocky soil?
WET BULB TEMPERATURE AND DRY BULB TEMPERATURE?