how much brick,cement,and sand required in 1cum
brickwork(1:4)
Answer Posted / manoj mall
for brick size 230mmx115mmx75mm (1:4) for 1cum
volume of 1 brick= 0.00198
say 12mmtk mortar on brick layer
so vol of brick 0.00267 cum
No. of bricks in 1cum = 1/0.00267 = 375 num bricks
volume of bricks for 1cum = 375x0.00198=0.724 cum
volume of cement mortar 1~0.724=0.26cum
add 15% for wastae=0.3 cum
add 30% for dry mortarof 0.3 cum = 0.4 cum
for cm 1:4 = 1+4=5
qnty of cement 1/5 x 0.4 = 0.08 cum
1 bag of cement = 0.035 cum
0.08/0.035 = 2.28 bag
sand = 0.08 x 4 = 0.32 cum
| Is This Answer Correct ? | 188 Yes | 48 No |
Post New Answer View All Answers
i have boiler of 35 tone and wanted dig out foundation is there any body to help me to carry out calculation for the foundation like
what is the type of earthing
what discoveries did you have in relation to your course?
please what are the required bars for a beams of 6mx6m and 450x300mm, one is continuous and the the second is discontinuous ..Its a commercial building (church)
How to do base isolation for RC framed structure using ETABS software?
why we are using stub column..? is it possible to construct steel stub column..?
sir i want to know that in L & T construction can we do our 6 months training proggramme cum placement???????
Cut Linten (RCC-1:2:4)on 10" wall - what should be the width and hight of cut Linten? Secondly, 1 X 1.6 foot,4" thick window sun/rain shed (Chajja)should consume steel,Cement, sand and Stone chips?
1.Why we are preferring 43 grade cement than 53 grade cement. 2. Approximate cost difference between 43 and 53 grade cement. Thanks.
Trapezoidal section footing calculation of Volume & its Area
Which brick is best for construction ,either fly ash or AAC BLOCKS
States some of the tool bars used in cad?
For elevated service Reservoirs what will be the output of each skilled carpenter and bar bender.
how much cement and sand consuptin in 4 inch siporex walls 100 sq ft
What are the points to be considered for calculating cement reconciliation. a)Do we need to deduct the wt of cement bags b)Do we need to adjust the qty due to wt loss during transportation, loading unloading etc or else each bag can be considered as 50 kg bag c)What is the proportion of mix cover block making.