We have three 33kv substations. All of them energised by
same source.When i am checking the phase sequence between
one substation to other substation
(like R Phase to R Phase) by multimeter i am getting
some voltage.Near to LT panels UPS panels are there. Can u
explain whether any possible to happen
like that. In Phase SEquencemeter is showing correctly
in both substations. How is it happen. Explain me.Explain
me communication signal will produce
Phase difference on this case.
Answer Posted / k.prakashchandra
you mean that you are having 3 nos 33 Kv bays ? How did you
check ? Furnish more details.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
What is the effect of positive feedback on the stability of the systems?
what kinds of Transformer oil grade is better for power transformer ?
what is the use of sdf?
What are the basic elements used for modeling mechanical translational system?
induction 3 phase motor terminal connection
i have a 1500kVA transformer what is the kWH meter i need to use?
What are the specifications for conducting earth leakage test as per IEC standard?
Why we used 690V in ACS 800 drives.Why dont use standard voltage like 415v or 1.1Kv
What are the main parts of central chiller plant? Explain the function of each stage.
I have 2 KW electric water heater.I am gonna use it in controlling water temp.so I needed to increase or decrease the heating capacity.is there any electrical-electronic circuit for varying the resistance & so current?
what is the meaning of WYE and DELTA in Electric meter?
Make a list observation on Transformer?
static chagre
Air circuit breaker safety
what is transient enclosure vltage , very fast transients, very fast transient over voltages