how we can calculate the capacity of a proposed canal in a
command area.
Answer Posted / khalil
first of all duty of the command area is determined. Then
we multifly discharege into acres. for example if duty 1
cusec/100 acres the area is 1000 acres then discharge of
the canal is 10 cusecs. if the canal shape is trapezoidal
then we put by hit and trail method varous d and b.
Is This Answer Correct ? | 8 Yes | 2 No |
Post New Answer View All Answers
What is fineness modulus ? and its sieve # ?
Which IS Code/American Code applied for coupler test of steel
what is the type of earthing
What is a projection line?
how to control PQI (Project Quality Index)
if mineral admixture add into concrete then what is the differences between full cement concrete & fly ash added concrete of their SP. Gr.?and for the changes of SP. Gr. what is the changes in concrete
What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?
Where is the worlds longest elevator and how long is it?
1.How much batten required for 1 sqm Shuttering. 2.how much pipe & clamps required for staging of 100 sqm shuttering at 5.0 m height.
How much cement is require in one sqft area in a G+3 residential construction.
how to check and keep control on the wastage of material at site
how to calculate steel for slab or footings?
how to calculate the length diamond shaped striupps in column
how many time use of plywood shuttering and IS code
If a slab concrete is placed with M-20 grade concrete, actually it has to be placed with M-30. what are the rectifications / measures to be taken after concreting is done.