Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete
by explaining all formulas involved.
Answer Posted / santosh
volume of trapezoidal footing = H/3{a1+a2+square root a1.a2}
here a1 = area in bottom of footing
a2 = area in top of footing
H = height of footing
if there is any doubt then call me on 09907027855
| Is This Answer Correct ? | 100 Yes | 32 No |
Post New Answer View All Answers
I want to know the material required per square foot in rcc roof. i.e. steel: kg/foot, cement/foot etc.
How much cement is require in one sqft area in a G+3 residential construction.
How much river sand contain the 6 & 10 wheeler truck? Or Maximum sand that any type of truck carry?
what is escalation?how it is done?
How to calculate dry of volume of concrete constant?How it comes 1.54 or 1.57
Define What is the distance between railway tracks?
how can we calculate steel value, depending on load
HOE TO YOU PLAN TO ACCHIEVE THE GOALS?
quantity of material needed for rubble stone masonry for 1:4 and 1:6
how much used soil in 1 brick of standard size?
how to prepare site mix design
what might be the problem faced in the near future if the M-sand is used in the place of river sand during wall plastering? (As per IS)
what is differences between ferrock and concrete ?
What are the methods of measurement? Describe it shortly
how much shouid be the rate for ready mix concrete per cubic meter