How du we calculate dry cement (in Bags) for any concrete,
also sand and aggregate? How many bags of cement does 100
cft of concrete 1:2:4 require? Procedure to calculate the
required amount. Also if there is any easy thumb rule to
find out.
Answer Posted / mayank jain
14.28 cft
| Is This Answer Correct ? | 6 Yes | 5 No |
Post New Answer View All Answers
Plasterers do how many sqm with spray plaster machine? By hand one mason does 10m2/day. How much they do in Dubai with spray plaster machines?
HOW MUCH STEEL REQUIRED FOR SLAB OF AREA 23'3"*18.3"? FOR SLAB HOW MUCH DIAMETER BAR WILL USE?
I am called for interview from north east power plant .so, I need some interview question which may help me.
In case if concrete box girder bridges how is the number of cells determined?
what is the tensile strength of 10swg and 8swg gabion wire?
material used for mendrel use to bend epoxy coated rebar
In tower foundation, on the time of 3 mtr pit RCC casting if water and mud is their surface of PCC then what will be do?
what pressure the NP2 class RCC pipe can sustain?
What is the general specifications of a bituminous pavement road?
silt%= silt volume/ silt+sand volume is this right?
What is the outturn of Ceiling plastering
How many kilo-newtons equals 1000 kilogram?
What is change order request?
In the roof of a pumping station explain briefly the components of a waterproofing system?
how to calculate the scour depth