how to calculate the steel quantity for beams & columns
also footing net?
what is the formulae for calculate the steel quantity?
what is mean by (100.3)plinth level?what is mean by 100.3?
explained it?
Answer Posted / sachin
TO calculate the steel qty first calculate the length of
steel as per drwg and multiply this length of steel to the
per meter wt. of the respective dia of steel. THIS GIVES
THE WT. OF STEEL IN KG.
100.3 plinth level indicates the RL of the plinth beam with
respect to the BM fixed for the plot plan.
| Is This Answer Correct ? | 32 Yes | 10 No |
Post New Answer View All Answers
What will you do if you encounter problems like accidents?
how to workable concrete cube test M-25 design mix
how to calculate the chair reinforcement length in slabs, footing or anywhere??
Can we use Polystyrene as a Bitumen modifier !! if so is it a good MS research topic ? and what type of laboratory tests will be conducted during Research work ??
IS code for grade of concrete for bamboo lintel????
Different sizes of Hollow blocks and its weight. Thanks.
Why are the bolts that hold steel rails together in oval holes?
I have a slab of 20cm thickness of 20m by 4m in wich we are installing 15 tons electric panels , and we have put 4 H-shaped columns under the slab but we have done many cores in the slab which seems very normal , can you help me by telling me how to calculate the bearing capacity of the slab or give me an idea if i should increase more columns Note: load distribution area 12*1.5 m2
Give list of building construction equipment & explain about them in brief. How much is output of JCB, POCLAIN, Steel cutting & bending machine, material hoist, tower crane?
I am called for interview from north east power plant .so, I need some interview question which may help me.
How to calculate Volume of Wet cement concrete for a specific grade?
when it is noted "JAMB SIM" what is the term "SIM" and what does it mean?
for Precast foundation howmany days required we can shift the foundation with american Standards i need reference with section any body can help
what else we can add rather than admixture in concrete to reduce the cement quantity?
the volume of cement req for 70cum of brickwork in 1:6 cement mortar is approx is equal to 3cum 5cum 7cum 1ocum