For G+4 storied building having 76000 sft per each floor,
can you prepare schedule in such a way that structure
should be completed with in 41/2 months and finishing be
completed with in 51/2 months?
Answer Posted / sanjeev kumar jain
Definately Yes. We shall require all the detailed drawings
& specifications of construction first of all. Now we shall
arrange the activities of construction in a bar chart
manner with overlapping activities. We will have to asses
the magnitude of the most time consuming activities and
thus allocate max resources to these. By continious mix &
match combinations of time & resources, we can certailly
work upon a schedule which is required subject to the
conditions that the level of resources as required in the
planning part are actually available and there is no
ambiguity in overall action plan.
| Is This Answer Correct ? | 7 Yes | 0 No |
Post New Answer View All Answers
in one hour , one 200 excavator , how much quantity (mcube)can load ? soil is not hard not soft
difference between fc and fc'?
if we know load bearing capacity of the soil and building load falling in each footing, then how to choose the type of foundation??? and if it is shallow foundation then which type of shallow foundation should be choosen i.e either strip or isolated or raft or combined or cantilever footing???????
what is labour consume factor in residential projects
01. a. Diagram of a slump cone…………… 1 b. Size of Slump Cone…………… 1 c. Volume of a slump cone by av. Dia method…………… 1 d. Volume of a slump cone by av. area method…………… 1 e. Volume of a slump cone by frustrum method …………… 1 f. Angles of slump cone …………… 1 g. Slump measured by slump cone due to…………… 1 h. Slump does not measured by cylinder / cube due to …………… 1 i) ii) i. Slump cone is to be filled in……………………..Layers.
for 16mm thick cement plastring 1:6 on 100 Sq.m.New brick work,the quantity of cement required is.
CAN V USE CRUSH SAND FOR CLAY BRICK MASONARY
225 mm thick RCC slab, how many ton load slab can carry? for example if 33 ton truck loaded with soil, truck having 6 wheels. slab can take load or not? grade of concrete is M35 and slab design Fe500, slab desing one way slab.
What are the advantages of building a dam on the river nile?
What is 1/8 on the architect ruler denotes?
What is zoning permit?
I am in India. Employer A got approval for my H1. But they have no job for me now. Company B is going to file H1 for me. They do not know about company A. Is there any way that I get approved H1 of company A transferred to Company B?
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.
As per Kandal suggestions, we have implemented rolling starts on 140 (+/- 5) degrees and we kept 3 rollars to complete the rolling before falling 125 degrees and the Aggregate AIV is below 22. But When the DBM bed is being rolled 3rd high viabration, (Before 1 plain & low ,2 high Viabrations), the aggregate is getting sharp edge agg. projections are damaged. As the literature is said that, the VG-30 Grade having better control the temp. susceptibility than Penetration grade. if so we could not get this problem at site. But we are facing on site. let me know.
can any one explain bar bending schedule of bems and columns and slabs ??