How to repair the Pavement quality conc used for toll
plazas if is giving hungry look or honeycombed ?
how much cement need to treat 100sqmtr of Damaged PQC
Answer Posted / pradeep
Honey combed concrete repair by
1. Pressure grouting with Polymer cement slurry. than
2. Filled up surface with epoxy or polmer mortar and
levelled it.
3. or by laying of mastic of 20mm or more thick and compact
it
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
What is meant by cad?
Does brick grows bigger every year?
Explain what is structural frames or systems?
I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations
Define What is diversion tunnel in a dam?
How much Tolerance factors like 1. brick work 2.plaster 3.painting 4.floor tiling 5.wall tiling 6.shuttering 7.concreting 8.steel
5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)
What is the zero value in quantity surveying
Requirement of cement, and steel 1:2:4 ratio concrete in 1128 Sqft area(Cement No of bags, steel in Kgs)
What is the worlds largest concrete dam?
Define Workability ?
How do you calculate the power of a centrifugal pump?
Can we weld hot rolled steel ASTM A615 ? Please Give the detail answer please thanks alot
What are the different methods for drawing an arc?
Dear Frds, How can i calculate the Steel for RCC Slab, Please provide one Example also, so that i can understand very well. Ex: Area: 1320.0 Sft.(44' X 30') Span: 15'(Default). Column Size: 9"X15"(6 No.s 12mm Rods) Please Provide Calculation Details. Thankyou. Satish