how many no of solid blocks and bricks required for construction of wall for 100 sqft?
Answer Posted / rrr
100sft = 9.3sqmt
for one brick thick masonry
std brick size - .2 x .1 x .1 mts=0.002m3/brick (for 1cum = 500bricks)
for 9.3sqmt = (1xwall thkness) x 500 x 9.3=930nos for 0.2mts thick wall
for solid block
std size - 8" =0.4 x 0.2 x 0.2 mts=0.016cum/block for 1cum = 63 blocks
for 9.3sqmt = (1xwall thkness) x 63 x 9.3=120nos for 0.2mts thick wall(8")
| Is This Answer Correct ? | 8 Yes | 18 No |
Post New Answer View All Answers
Define What happens to Load at yielding ?
Determine the production capacity of a treatment plant for a city of 1,250,000 population. Assume the specific consumption per capita of 15ol/c/d, non-domestic water use of 30,000,000 m³/year, and UFW of 12%.
Explain how you can use different dimension tools in CAD? What are the different dimensions available?
i) Distinguish between Theodolite and dumpy Level? (Marks-8) ii)Distinguish between Viscous and Turbulent flow? (Marks-8) iii) Distinguish between nominal and design mix? iv) What is standard sand? v) Explain the term plane stress? Vi) Differentiate between principal plane and principal axis? Vii) write short notes on Elastic limit of structural steel? viii) Write short notes on stress concentration? ix) write short notes on "Grading of Sand" ? x) How many grades of concrete are there under standard concrete?
How can we convert weight batch to volume batch for m30 mix
how much need sand and cement for 1 cft roof construction?
How to calculate the weight of sand am 20mm course aggregate in 1 c.m M25 concrete Which use 400 kg of cement ?
What you understand by building codes?
how statics is different from dynamics
What is the maximum strength of cub compress strength in one cub testing
How to calculate Acctually Brickwork Quantity in Honey Comb Brick in circular Soak Pit
what is Quantity of stone and sand required for one cubic meter of stone work (UCR)
What is chemical composion test
hi every body..i have applied for RRB section engineers CIVIL.i wanna prepare for that,so can any one suggest me some books and where can i get the syllabus for this..i would be vry greatful if any one can help in this regard
Design a cantilever type retaining wall to retain sand for 4m above the ground. The sand fall slopes at the rate of 1 vertical to 2 horizontal. The weight of sand is 18000 N/m3, the angle of repose being 30. The safe bearing capacity of the soil is 200 kn/m2 at 1/25m below the ground level. Use m 15 concrete mix.