how cubic feet cement,sand,aggregate required for 1 cubic feet
ratio=1,1.5,3
Answer Posted / r.suresh
cement= 11kg
sand = .012cuft
aggregate=.024cuft
| Is This Answer Correct ? | 9 Yes | 11 No |
Post New Answer View All Answers
What happens when,in Prestressed girder the HDPE duct and cone size is provided more than required? (technical answer expected)
For what purpose bedding is used under storm water drains?
What are the Types Of DPC and its Thickness used?
100mm block work 64 bags of cement used 150mm block work 286 bags of cement used 200mm block work 20 bags of cement used patly work (M15) 293 bags of cement used mortar ratio is 1:5 how to calculate volume of sand in cum & no. of bags
225 mm thick RCC slab, how many ton load slab can carry? for example if 33 ton truck loaded with soil, truck having 6 wheels. slab can take load or not? grade of concrete is M35 and slab design Fe500, slab desing one way slab.
What is the average density of soil?
foundation details for 25 ton weight Furnace on 2 supports and 2 tilters
pile load testing procedure
What is eccentricity in laymans term Can't understand bookish language .please explain in easy way.
Hi how r u ? hope you are fine there . Please can u tell me tha Design life of Buildings as Per ACI CODE 318-99. It will be a pleasure for me .Thanks in advance
How to calculate material and labor required for 100 m2 plaster?
how many numbers of 4inch bricks and get consumed in 9 inch BB masonary wall in cubic feet.plz send my below e.mail adress
Which IS Code/American Code applied for coupler test of steel
What is the difference between chamfer and fillet?
I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations