Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How to find out kvar from any particular load capacity give
a formula

Answer Posted / joel q.

Ex. If your load is 100KW @ 0.9 power factor.

Your KVAR load is:

KVAR = 100*Tan((arccos0.9))

Is This Answer Correct ?    8 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How calculated single phase induction motor req. Capacitor?

1521


What is the mechanism of WTI

1737


What happens if we run alternator on under frequency? 

2048


who can measure the size of power cable?

2094


What is an automatic controller?

1091


Is a contactor (or master relay) required between incoming lines and a VFD? The question goes to safety. If a contactor were used before the VFD and an e-stop engaged then the motor will coast to a stop (i.e. VFD loses power) instead of stopping much faster if the VFD braking fucntion were used. It would make more sense to keep power on the VFD.

2098


what are the accessories need to be added while doing estimation for the following: 1.MCCB 2.MCB 3.ACB

2045


A generating system will have a total capacity of 300 MW. Find the probable forced outage when the capacity is supplied by two 150 MW units. The operating probability of all units is P=0.98 and forced outage probability rate Q =0.02 .

2573


how to select proper cable for ct wiring so that drop within the limit.

1919


HOW DO I CALCULATE THE SETTINGS FOR THE DIFFERENTIAL PROTECTION OF A 12kV/6.6kV, 6MVA,DYN11 XMER WITH PRIMARY SIDE CTR 400/1 AND SEC SIDE CTR 600/1?

2541


What is meant by analogous system?

1216


Briefly describe your ideal job?

2923


Phase control and integral control are used for?

2252


What are the components connected in between the power supply coming from an electric pole to HT & LT Panels in a large commercial building or how the power supply connected from Electric pole to Transformer & then to the HT & LT panels of a building? Please send me answers via mail, my id is yogiagarwal@gmail.com. If possible, please give a line diagram.

2017


1.Can we use 6.6/11KV 300sq mm xlpe 3core cable for LT use (415 Volt). 2. If we use it for LT then what is the current rating

1696