what"s the formula find the cement consumption for brick work
23 thick wall 1 m3?
Answer Posted / guest
(1/(0.2*.1*.1))=500
=500*(.19*.09*.09)=0.76 cum of brick volume
=1-.76 = 0.24 mortor volume
=0.24
Is This Answer Correct ? | 86 Yes | 26 No |
Post New Answer View All Answers
What is the frequency of sampling for the materials of cement,Fine aggregate, Coarse aggregate .and refer which code
sir how can we find the cement and sand required for making 4" drop
How to calculate paint drums per meter square
contractor receive 100 MT steel.after compliting the work the contractor refund 90 MT steel.How reconsilation of steel done?
in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh
How to calculate cement and river sand material Qty for waterproofing base coat and finish coat
Explain what is zoning permit?
What is the sugested procedure of water purification for public supply?
how to calculate quantity of bricks in circular manhole with examples.
How to calculate construction cost of residential building in mumbai
how to take the quantity of block work and plastering 1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate
How to use of me trial wall plaster 6mm , 10mm par sqm. use in sand and cement ?
what post do you prefer to work in this company and why do you think you can serve better in such position?
What is kn measurement?
types of piles detail,