Answer Posted / kuntal desai
These are (generally) contractual requirements of a project.
FAT - Factory Acceptance Test
Once FAT is checked/signed by customer at manufacturing
end, the equipment is ready for dispatch.
SAT - Site Acceptance Test
Once SAT is checked/signed by customer at site, the
equipment is ready for handover.
| Is This Answer Correct ? | 82 Yes | 2 No |
Post New Answer View All Answers
How do you know the code has met specifications?
How do you test for the coockies for a web application?
need answer interviewer will ask me about all project which i mention in resume or presently i'm working??please reply tomorrow is my interview
how deployment phase of SDLC differs in product based and in service based company ?
Unit Testing can be done by using Nunit?
Hi friends, currently i am working with banking domain project in the part of testing..what kind of questions will be ask at interviews.. can anybody listout the project oriented questions which are asked in interviews...
What is the Diff between Code Walkthrough & Code Review? What is the diff between walkthrough and inspection? What is meant by GUI Testing?
How do your characteristics compare to the profile of the ideal manager that you just described?
How to test the below code and write test case? Prove that this code is wrong? int add(int a ,int b) {return a+b; }
What is the difference between functional testing and integration testing?
What is the difference between functional requirement and non-functional requirement?
Enlist some bug status along with its description?
What is the difference between coupling and cohesion?
Explain the defect life cycle.
how will you estimate of your website?