Why bent up bars provided in R.C.C slab
Answer Posted / agha zafar
it is actually economization of material. normally, for
fixed ended beams positive (sagging) moments are present at
the mid span and negative (hogging) moments at the supports.
so bottom steel is required at the mid span and top steel
resists negative moments at the supports. a bent-up is
provided to take the steel on the top at supports as bottom
steel is not normally required at at the supports (only
nominal steel is sufficient). hope it'd help!
Is This Answer Correct ? | 311 Yes | 19 No |
Post New Answer View All Answers
Are cruise ships built for the transatlantic run?
what is the max. area can we apply the plate load test ?
construction workers how much time take one work or qty
Define line type?
in a corner footing of a building, column lies in one corner. in this condition i want to know if the reactive pressure of soil will be uniformly distributed throughout the footing or will be uniformly varying as in the case of eccentrical loading.
residential buildings,mixing of concrete,structural,construction material,site handling.
A sieve analysis results in 100% retained in no. 50 Sieve, the fm is?
Define a polyline?
what post do you prefer to work in this company and why do you think you can serve better in such position?
How to calculate cement and river sand material Qty for waterproofing base coat and finish coat
States some of the tool bars used in cad?
Define What is the distance between railway tracks?
Rate analysis of 150mm, 100mm, & 230mm thk BBM work
how to find hardness of water?why it should be determined?
If we are providing concrete joint in every 10m with water stopper in water tank wall then is it necessary to cut the steel at joint section?