How can we calculate quantity of slab, beam @ column ?
Beam should be calculated by deducting slab thickness or
slab should be calculate in to in ?
Answer Posted / sjtbehera
it is easy
length x breadth x height = qty.
if you calculate slab, if you adding beam thickness then
while you calculate beam you will deduct the qty. of beam
from qty. of slab
| Is This Answer Correct ? | 47 Yes | 10 No |
Post New Answer View All Answers
all technical question
How many axes do cartesian coordinate system has?
what is total volume of ingredients used in concrete accordingly
Can we use the flyash bricks in brick bat coba?
what is a well
What is the procedure and technnology behind jointing of prestessed block in Delhi metro rail project.
How much the quantity of Dry material of Crush for 1:2:4 Concrete, using pan 3/8'' down....
How to calculate carrying capacity of the existing water supply trunkmain
why do we provide haunches in rcc box or underpasses?
Material calculation of cm 1:6 for 1sqm
what is BPM in concrete demolition hammers. what is better a higher value or lower
1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.
what is the coefficient for running feet to cft coversion both area and price
why we use aggregate,sand with cement in concrete?
SAND AND STONE AGGREGATES WASTAGE PERCENTAGE IN CONCRETING WORK?