Answer Posted / kesavan.b trichy,
On Load Tap Changer in a device which works under running
condition to increase or decrease the voltage level of the
Primary & Secondary Side... It is preferable to provide @
HT Side why because in HT Side the current rating is low
while in the LT Side current is so much high.... as we done
the operation of tap changing under loading condition at
the LT Side a huge spark will occur & Damage the
Transformer... That is why only the OLTC is placed on HT
Side
| Is This Answer Correct ? | 9 Yes | 1 No |
Post New Answer View All Answers
what topics we have to concentrate for power grid et.written test.and tell what to read for english synonyms and antonyms.
sometime battery charged and then automatically charged when rectifier ON conition, is there any chances please clarify the same.
2 v/500amp/hr to 1.80vpc at 20 degree celsious 2v/5ooamp/hr to 1.75 vpc at 77degree farren .this is the capacity of a battery .what is the meaning of this . can i get a detailed explenation
While converting delta into star or star into delta ,the three values of resistances remains unchanged .Find out the value?Let In star R1=x;r2=x;R3=x On converting into delta,R12=x;R23=x;R31=x Find the value of x
How relay coordination has to be done? what are the inputs are required for this? Please explain this with calculation method?
If we want to change a contactor of faulty one what are the conditions want to fullfil
in indoor type circuit breakers why only the corner breaker trips specially during cold season. What is the reason.
What is DC series motor?
Draw the vector diagram and condition for the following: 1) Dyn1 2) Ynd0 3) YnYn0
hi this is hema, r there any books in particular for the preparation of the APPSC-A.E.E(electrical), if so please mail me the names ... thank u .
Advantages/Disadvantages of earthing of neutral bus on MSB instead of separate neutral earthing for transformer/DG sets feeding to MSB
How earthing/grounding done in aeroplanes and ships.
how to build a network which step down 415v to 1v rms
"TRANSFORMER MODELING AND ANALYSIS" MEANS WHAT AND WHICH TOPICS U READ IN THIS
Can 33kva/415v transformer be run underground? If the answer is yes why and if the answer is no why?