what"s the formula find the cement consumption for brick work
23 thick wall 1 m3?
Answer Posted / sri
volume occupied by brick=100x.19x.09x.09=.153cu.m
volume of brick 1x1x.23=.23cu.m
volume of joints=0.23-0.153=0.077cu.m
mortar to fill up frogs=100x.10x.04x.01=.004cu.m
total mortar=.077+.0040=0.081cu.m
| Is This Answer Correct ? | 52 Yes | 49 No |
Post New Answer View All Answers
Explain the mechanism of cavitations in pipes and drains?
What is the difference between tor steel and tmt steel?
I have an plot with area 35*47 = 182.77 sq yards. Out of this iam planning to construct house with 1350 sqfeet each floor .iwanted to build a G+2 house.Need cost estimation for each item
What is GSB gradation
a) Difference between Ghol , Chimney & fly ash bricks b)Floor to floor height is 3m , rise=15cm , tread 20 cm , how to design staircase means steps landing
What is construction mitigation management?
Explain the term 'Gross unit rate' and identify the items that may be included in the gross unit rate.
Hi.. Can i get hel in finding HPCL previous year question paper? plz help me in finding thiss..
What is the likely strength of a 1:2:4 concrete mix?
Mention what are the composition of a landfill?
what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?
What is gravity flow?
How Can I know the wastages(%) of each work added in estimating the quantity of construction materials?(Eg. Ceiling Work, Brick Work,etc....)
I used Etabs software to analyse a high-rise building. And I want to use templated UBC-codes inside to calculate the Seismic load. My question is: whether or not I have to control the seismic load by base shear load which is manual calculation? (just for more clarification: I can control this by input the scale factor into Eartquake definition in Etabs) I would highly appreciate your answer.
Why the finite element method is lower bound solution?