Answer Posted / praveen
3 Phase O/C + E/F + Highset
0C 0
50/51 RYBN
Numerical Relay
Lowset O/C -Is
Highset O/C -Ihs
Lowset E/F -Os
Highset E/F -Ohs
O/C Is = 20-200% Step 5%
E/F Os = 5-80% Step 5%
HS O/C = (0.2 to 40) x In step of -
0.2 In or disable
HS E/F = (0.1 to 20) x On step of -
0.1 On or disable
Time Characteristics available -
NI, VI, EI, or Definite Time
TMS : 0.1 - 1.6 Step 0.05
Site selectable Trip time Char.
Highset can be disabled
Display of Currents, Trip count
Self supervision feature
£ 0.25 VA on CT/Phase
Not applicable
0 to 60 C
< 2kg £ 10 VA
1 N/O Contact for self suprvn
Draw out
121 x 158 x 224
113 x 142
20-110V AC / DC or
88-264V AC / DC
1 AMP or 5 AMP
(site selectable)
4NO or 2NO + 2NC
| Is This Answer Correct ? | 15 Yes | 1 No |
Post New Answer View All Answers
how we arrange the hv side with delta connection in case 33/11kv of transformer.
why star point of HT motor not earthed?
I have a current transformer with 1 main reading meter with transformer outside the building and a control panel having 5 CT reading meters with black round coils inside the building. I want to know, A) when current pass through the Transformers, will the current be reduced or be the same and after that B) when current pass through the CT meters with black round coils, will the current be reduced or be the same. C) in the above process will the reading of the main meter be same or different, from the total reading of all the 5 CT meters.
hi this is hema can anyone mail me previous years questions for the APPSC-A.E.E (in electrical stream.) ......thank u.
i need the details about bhel exam.how to apply for that.please send to my email-id.thenmozhi2k7@gmail.com
What is the difference between single core 2 wire and single core 3 wire system? Which application we are using this? and for What purpose we are using this?
What are the special cables required for explosion proof wiring?
what are the installation procedure of high voltage power transformer,CT,CB&PT?
How to Calculate KA Rating of Main LT Panel
Explain about p.t?
How to calculate no of EARTH PIT? Describe the formula as per IS standard?
importance of reactive power management
What will be the impact on motor performance if a LT motor is rewound with changed motor winding data as given below:- Original winding data: total 04 wires = 02 wires of 17 SWG + 02 wires of 16.5 SWG. Changed Winding data: total 03 wires of 15.5 SWG wire size Motor rating: 160KW, 740RPM, 415V, ID FAN application. Normal Running Current = 95% of FL Current.
how to changeover ups in this power failur time?
1.4 What is meant by CT knee point voltage and how would you determine it