how the slump and Compressive Strength of concrete cube is
performed in a civil engg lab ?
Answer Posted / patricio baluga jr
Fill up the whole cone up to the top with some excess
concrete coming out of top, then repeat tamping 25 times.
(if there is not enough concrete from tamping compression,
stop tamping, add more, then continue tamping at previous
number)
Remove excess concrete from the opening of the slump cone
by using tamping rod in a rolling motion until flat.
Slowly and carefully remove the cone by lifting it
vertically (5 seconds +/- 2 seconds), making sure that the
concrete sample does not move.
Wait for the concrete mixture as it slowly slumps.
After the concrete stabilizes, measure the slump-height by
turning the slump cone upside down next to the sample,
placing the tamping rod on the slump cone and measuring the
distance from the rod to the ORIGINAL DISPLACED CENTER.
Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
How to arrive the co- efficient of all civil activities? For ex:- painting-enamel in wooden doors. co efficient is 1.8. How this is calculated
in the construction of residential building what type of tank are used?where?why & what is its purpose?
In the present situation of ban on mining sand from rivers,can we go for formation of earth dam filters viz;Horizantal sand blanket,inclined chimney and filters under rivetment with crushed rock sand of 6mm down size.If so what are the specifications and is there any codal provision for its authentication?
a) we have 30nos., 300mm dia, 4m length double under reamed piles.calculate excavation quantity.b) tell concrete qty. also.
how do you calculate the quantity of steel,cement for plinth beam. (example size 41'*0.58'*1.08')
Explain the various stages of the project planning process in construction?
how to calculate number of bitumen for road asphalt
what is thumb rule for calculating the size of ISMB required for a particular length of span
For 1 bag cement how i will calculate sand and metal aggregate;Here the mix proportion is 1:2.49:2.38
as per is code, what is the minimum content of opc and ppc cement for rcc structure
What is meant by cartesian coordinate system?
what is difference between fluidity and workability also how palsticizer works
How to calculate plastering for elevated water storage tank
Forces in a Shear Wall are in plane or out of plane ?
what is the weight of 6000 psi concrete in lb/cft?