why we always consider Bulkage due to the voids only for
the Fine aggregates not for the Coarse aggregates
Answer Posted / bhushan narvekar
When moisture content is added,a seperating film is
formed with fine aggregate only .And the coarse aggregate
colld not form the film.
This seperating film is responsible for the bulking
of sand i.e fine aggregate.
| Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
what is thumb rule for calculating the size of ISMB required for a particular length of span
qty. of cement & sand required (100sq.mtr) for fixing of floor and wall tiles also fixing of marble stone on the floor
what is stressing
how many numbers of 4inch bricks and get consumed in 9 inch BB masonary wall in cubic feet.plz send my below e.mail adress
Why should pumping be not used in case of concreting work?
How much permissible bearing capacity requires for open footings(isolated) and what type pile foundatuon prefering for coastal areas?
can stub column take the load as main column
why development length = 50D . why not 100D
how many litres of enamel paint required for 5000 sft of site??
What is chemical composion test
Dear Sir, I work in hydro project. I want to hire Scorpio/ Bolero on monthly basis. But how can i justified its amount (Hourly basic). Please solve my problem
what is directivity effect?
what does the grad of cement shows (denotes)?
What is the difference between yeild strength and compressive strength of steel???
How to determine thee cut length for steel reinforcement bars in R.C.C design