Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How you Confirm the Hard stratum for Driven cat in situ Pile
work?

Answer Posted / suresh

while driving the hammer if the pile penetrates into the stratum only for one cm for three to five releases of the hammer, it is considered to be hard stratum.

Is This Answer Correct ?    2 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Form where IS456 is adopted in 1978?

1968


What happens when,in Prestressed girder the HDPE duct and cone size is provided more than required? (technical answer expected)

2097


Define What is the difference between routing maintenance and major maintenance in school facilities?

1186


What is a projection line?

1164


types of piles detail,

2283


In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

2135


How does a traffic light signal work ?

2275


manhole chamber having height of 2300 mm and thickness of brickwork is 230 mm and dia of opening covering is 560 mm and bottom length vertical is 1500 mm (1:4) brick masonry and plaster 12 mm on both sides..how to estimate the no bricks used with mortar cement bags and sand for total chamber including plaster.

1749


Explain the various stages of the project planning process in construction?

1142


within an emergency scenario what are the safe systems of work a coss can setup as part of is duties

2112


How do you calculate the unit weight of concrete?

1113


a solid steel rod length 2m dia and 20mm vertically hangs from celling and has a collar firmly atteched to it. above the collar an annular rubber washer of 40mm th. having stifness k = 5n/mm is placed. determine maximum stress in the rod caused by mass of 5 kg falling through a height of 1.2m.

2340


what is the code provision for acceptance of fineness modulus range for fine aggregates in design mix

5178


how can we calculate steel value, depending on load

2119


Formula of mid span bar