Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete
by explaining all formulas involved.
Answer Posted / mohd.younus ali , je (pr )
Top Length = L1
Bottom Length = L2
Top Breadth = B1
Bottom Breadth = B2
Depth = D
Then simple formula is
(L1+L2)/2=L
(B1+B2)/2=B
The Quantity of Concrete is = L * B * D
| Is This Answer Correct ? | 16 Yes | 51 No |
Post New Answer View All Answers
Wat is meant by Aecron brick?
What is the basic difference between OPC
How to determine thee cut length for steel reinforcement bars in R.C.C design
In the design of bridge arguments what considerations should be made to select the orientation of the wing walls?
An interior designer designed a rack with the given dimensions. The dimensions are in feet. This coplanar frame repeats at every 5feet and constitute a space frame. The total length is 120feet. Which steel member will you suggest? A square bar, A square tube or a circular tube. Explain.
What is packing Factor ?
Which is stronger solid steel rod or hollow steel pipe?
What is the strength of cement?
Why are the bolts that hold steel rails together in oval holes?
What are the steps involved in the concreting process?
how many running meters in one kilogram of 4mm pvc coated chainlink fencing
how can i calculate cement in brickwork
how much concrete solid/hollow block are manufacture per 50 kg cement bag in differnent sizes like 400x200x200mm, 400x200x150mm, 400x200x100mm. And need proper ratio as per sale quantity. pls send my mail mathi7599@gmail.com searching last two years not yet get pls find and enclosed pls. need practical analysis.
if in column reinforcement lower dia connect to higher dia then from wher we want to start higher dia steel
to draw bm diagrams for portal frames under different loadings//