Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete
by explaining all formulas involved.
Answer Posted / mohd.younus ali , je (pr )
Top Length = L1
Bottom Length = L2
Top Breadth = B1
Bottom Breadth = B2
Depth = D
Then simple formula is
(L1+L2)/2=L
(B1+B2)/2=B
The Quantity of Concrete is = L * B * D
| Is This Answer Correct ? | 16 Yes | 51 No |
Post New Answer View All Answers
can any one give me sample question paper of BHEL at mdansari86@gmail.com as i m appearing for the same exam.
I HAVE APPLIED FOR 20TH UES ARMY. I WANTED TO KNOW WHEN WILL I RECEIVE CALL LETTER FOR THE SAME.
What is the strength of 1:6:12 mix?
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
What is Density of cement, sand & aggregate ?
Draw a neat sketch showing the 'throat' of a welding in a plate girder ?
can u plz send me ntpc placement papers(civil engineering) at mohit_verma21@yahoo.com
sir I got selected in rail vikas nigam limited and they call for interview but i don't what they will ask in interview please guide me if you have any experience
Suggest how many column, beem, etc required for 30 mtrs x 21 mtrs width x 8mtrs height for industrial shed of ground floor. I want to know the quantity of tmt steel consumption and Concrete consumption for budgeting
cud any one send me tech quest paper(civil engg) at tarizus@yahoo.com
HOw much % of premium on DSR-2013 currently
minimum number of bars in a beam? minimum and maximum column size and beam size ? minimum and maximum aggregate size used in multistorey residential building for columns,beams,slabs?
pls mail some more tecnical qustions at msaranya2610@gmail.com
PLS.......... ANY ONE CAN FORWARD ME PREVIOUS QUESTION PAPER hpcl civil engg
can you please tell me what the current rate of construction material and different construction labourers charge in bangalore ???