Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete
by explaining all formulas involved.
Answer Posted / mohd.younus ali , je (pr )
Top Length = L1
Bottom Length = L2
Top Breadth = B1
Bottom Breadth = B2
Depth = D
Then simple formula is
(L1+L2)/2=L
(B1+B2)/2=B
The Quantity of Concrete is = L * B * D
| Is This Answer Correct ? | 16 Yes | 51 No |
Post New Answer View All Answers
Difference between lime, distemper and plastic emulsion?
Which is the direction of negative angle?
what is the composition of good brick ?
Which tests are performed on soil to decide the type of foundation to be provided.
what is a well
what is concrete canvas?
what is the water cement ratio for plastering
what is the soil bearing capacity for a 5 floor multistorey residential building and which type of soil ? what is plinth beam? in wall load calculation center to center column distance is considered or not/
Howmuch bend to be provide for 200/600 BEEM
In few lines, please be elaborative on extras and talents that make you a potential candidate for the post:
If we don't have drawing for Excavation of building,At what rule we will go for excavation and how much depth will go for a villa?
What do we mean by partial moment release ??
How much cement and sand required for 9"brick wall per square metre
pls give me some basic informations in construction of a structure?
How and where are aqueducts built?