Answer Posted / ahmed
Daer
the amount of cement in m3 according to ACI code with
mixture ratio 1:2:4 is 300 kg
and the amount of sand is 0.42 m3
and the amount of cource aggregate(gravel) is 0.84
regards
civil engineer
Ahmed Sami
IRAQ
Is This Answer Correct ? | 9 Yes | 5 No |
Post New Answer View All Answers
what is labour consume factor in residential projects
punj loyed and sapurjl palanjl
How to calculate the area in squarefeets ?How much area of sqft for this measurements?East 53.3ft West 54ft North 47.7ft South 51.1ft ?
Define graphics window?
which is the cheapest type of flooring (say for using for 6 months in a factory building & dismantling it)?
RR masonry rate analysis
How to Calculate Materials Required for PCC 1:4:8 for 1Cum & Brickwork 1:4 for 1Cum & Plastering 1:4 (15mm Thick) for 100Sqm & RCC 1:4:8 & 2mt ( L1=1mt & L2=1mt ) length of 12mm Steel bended in 90degrees what is the formula to calculate Weight & Actual Length ?
1m square 20mm plastering how much of water need curing work
In the different classes or grades of concrete, what is the difference between C20, M20 B20. what are the letters C, M, and B stands for.
Why are pull-out tests performed for soil nails?
What is binding spacing of the rebars at lapping zones.
Define What is the distance between railway tracks?
rimmer in pile foundation
How to convert 20 dia bar to 16 dia bar in beam without reducing the steel weight
How to use of me trial wall plaster 6mm , 10mm par sqm. use in sand and cement ?