suppose if we have 2 nos 500 KVA DG set & want to take the
power from both DG set at one busbar so will have to
synchroniz first its phase R to R, Y to Y, B to B, & also
will have to synchroniz its voltage & frequency
Is This Answer Correct ? | 16 Yes | 0 No |
Post New Answer View All Answers
how can service sitting be setted for MCCB?Example for sittings IR (CURRENT RATING),IS(CURRENT STARTING)IO (current operating)?
what is the meaning of WYE and DELTA in Electric meter?
As per the Anchor capstan motor specification, full load current is 200A. starting current is 1750 A and acceleration time is less than 8 seconds. Please guide for selection of cable size.
Why different Pressure switch used in marine boiler water circulation system
What willbe change in programming when we use 5/3 solenoid inplace of 5/2 in operating of a cylinder?
What happens if i apply 500V to 440V rotary Switch ?
What type interview questions ask in Electrical technicians
What is the lifetime of a Thyristor? Is there a recommended lifetime for thyristors after which they should be replaced?
What is the HVDC Transmission System? What are the conditions applicable to lay an HVDC Line?
what is the formula for computing cable tray size & capacity
What is difference and reason b/w -48V BTS system and 24 V BTS system. Plzzzzzzzzz tel me.
Why ground terminal is used in pot meter 10k ohms
Write down the name of 2 lady Bir Pratin of Bangladesh
limitation of conductor height on ground when we consider EMC
hello!my name is sheikh iam preparing for indian engineering servieces,please send me the old question papers..to sheikhshaazforjobs@gmail.com