Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how can we calculate the cutting length of 10,12,16,20 and
so on iron bars for 45 digree and 90 digree bents plz tell
me if there is any formula or tabel to find it

Answer Posted / 03265523

for example if any steel take 1.0 meter cutting length

density= weight / volume

density of steel is 7850kg/m3
volume of steel = areaX length=3.14xD2/4*1.0
weight of steel for 1m is= density X volume
= 3.14D2x1000*7850/1000*1000*1000
=D2/162 (square of D/162)
where D is the dia of bar in mm
for 45degrres =cutting length-1 * dia of bar* no of bends
for 90 degrees= cutting length-2 * dia of bar*no of bends

Is This Answer Correct ?    258 Yes 57 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What are the different approaches in designing the floors of the service reservoirs?

1187


"Gates of the dams are generally designed of curved shape". Why?

2068


Currently my house construction is going on but we just realized that the portico earth beam couldn't connect with the original earth because the beam rod not extended so Please advice

2654


How much Tolerance factors like 1. brick work 2.plaster 3.painting 4.floor tiling 5.wall tiling 6.shuttering 7.concreting 8.steel

1854


What are the steps involved in the concreting process?

1360


Rate analysis of Vitrified tile in cement mortor 1:3

4494


What are the delays in construction projects due to approvals from owners? How can we analyze them in different prospective? Whats their affects and effects on presently going work?

2115


how to design and calculate materail quantity for concrete speedbreaker ?

5999


Explain what is progress payment?

1172


What is the zero value in quantity surveying

2552


how to calculate cost of raw materials of a building for 1000 sqft & also consolidated cost of labour in a 1000 sqft building

2861


please send latest placement papers of hpcl officers trainee test. i will be very thankful to you.

2322


Explain what is change order request?

1138


What expenses counted in contingencies and how much it is in related to built-up area of the building.

1786


Why do we not deduct steel volume to find actual volume of concrete in practical as we have studied that,,, actual volume of concrete = volume of column- volume of steel pls explain with reference of IS code?????

2079