HOW TO FIND OUT THE QUANTITY OF CONCREATE
Answer Posted / zuhair shamsedeen
by checking from structure drawing and arch - drawing
| Is This Answer Correct ? | 2 Yes | 4 No |
Post New Answer View All Answers
usually hand broken stones are used for cement concrete 1:4:8 in foundation of single /two story houses with a view of economy in construction.what advantages it will give if you use machine crushed stone in place?
what is called the inverd level of mabhole chamber?
How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 100 microns?
for 16mm thick cement plastring 1:6 on 100 Sq.m.New brick work,the quantity of cement required is.
column at edge of a framed structure is uniaxial or biaxial. and is an interior column is biaxial
indian standard split spoon sampler
how we calculate the vol.of wet concrete..?
Why joints are provided?
In the different classes or grades of concrete, what is the difference between C20, M20 B20. what are the letters C, M, and B stands for.
what happening if we casting HV shunt reactor foundation pad at 50cm height different time (One day difference)
how many cement used in single story residential building per sqft
can any one explain bar bending schedule of bems and columns and slabs ??
how to compute slab reinforcements on step by step procedures??
how to find hardness of water?why it should be determined?
A 16 pile group, consisting of diameter concrete piles, were cast in situ in a clayey soil whose unconfined compressive strength is 1100 psf. Each pile is 60 ft long and the pile spacing is 2.5 times the pile diameter.The water table is at the ground surface and saturated unit weight of the clay is 118 lb/cu.ft. using a factor of safety 3 and a reduction factor =0.45, compute the allowable capacity of the piles acting as individuals