Answer Posted / munish sharma
In Rocky Area the soil resistivity comes out to be very
high.The overall grounging structure is based on following
criteria
1.Area Of the Switchyard
2.Surface Layer Resistivity
3.Soil Structure
4.Safety PArameters
5.Fault Current Distribution
There Are Certain Techniques in case of HIgh Soil
Resistivity as
1.Deep Groung well Earthing
2.If area is limited of the Switchyard,use Remote grid
along with main grid buried in low resistivity material
3. Soil Treatment
4. Use Grounging rods to take effect of deeoer low
resistivity layers
Is This Answer Correct ? | 6 Yes | 2 No |
Post New Answer View All Answers
what is the synchronous timer ? and it applications.
What is synchro?
Approach of a cooling tower is the difference between temperatures of what factors?
Differentiate between induced emf and self inductance?
i have 3500 amp load and select current transformer and perches.how i calculate .please understand
Electromagnetic torque developed by the motor is compared to shaft torque. A less B same C depends on motor design D more
What are the functions of different probes used in cro?
can mini-curcuit supply MIL-tested transformer !
how freewheeling diode improves the powerfactor
draw the block diagram of fire alarm?
1.why should we connect the measuring instruments in l.v side in short circuit test of a transformer? 2.why the power factor is less in open circuit test of a transformer?
If I have 3 essential main switch board and 3 incoming electricity ,but only 1 genset running is that possible.
We have two APFC panels in same station. I need how to connect CT in two APFC panels.can we take one CT in series connection or two separate CTs.
What is the formuala to calculate the rating of motor protection circuit breaker
how to do the ductor test?