Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete
by explaining all formulas involved.
Answer Posted / rakesh suthar
h/3(area of bottom + area of top+ under root area of
bottom * area of top)
| Is This Answer Correct ? | 155 Yes | 39 No |
Post New Answer View All Answers
100mm block work 64 bags of cement used 150mm block work 286 bags of cement used 200mm block work 20 bags of cement used patly work (M15) 293 bags of cement used mortar ratio is 1:5 how to calculate volume of sand in cum & no. of bags
what is the relation between pitch of steel and depth of slab?
Can inverted beams used in pipes during construction? If yes, explain how it can be implemented?
What is chemical composion test
How do you compute moisture correction using the parameters gathered from Nuclear Density Gauge Apparatus and the moisture contents results from the lab.?
what is diffrence between catchment area,watershed and basin?
how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.
how much repeitation for conventional and maivan formwork?
what is anchorage length,lap length and (dont remember the last one)
what is labour consume factor in residential projects
I am a civil engineer . I am also selected for sbi clerk interview which is to be held on 4th May2010 is there anybody resembling the same? what question can be asked and what should be the probable answers?
what is the max. and mim. height of vertical post in informatry sign board which is used in highway projects.
Why are steel plates inserted inside bearings in elastomeric bearings?
How much of the strength of concrete comes from post- production curing?
What is the difference between yeild strength and compressive strength of steel???