1. if only 1 slab of a floor get sagged, how could be it
repaired?
2. if any footing gives the cube result, after 28 days less
than 16 n/mm2 in spite of 20 n/mm2 what are the remedies ?
Answer Posted / venu gopal
2 reasons for saging.1) bad staging/supports. 2) bad
design. any hw if it sagged it does noteffect the next slab
casting we can cast the next one. as far as repairing of
1st slab is consern we should have a graphical
representation of sag and find out the lowest level and
highest level plot them and with the help of this date we
can fix the floor level ilttle elevated than planned and
the sagged area should be concreted (screed concret) with
good mix as per site condition.
2.if it is a big footing we cannot remove and redo. so
remove the top 200mm concret by chiping and use proper
bonding agents and introduce few more rebars through the
coloun and anchor them to the old footing and change the
shape of the footing to a triangular shape with rebars and
re concrete the top surface and additional care to be taken
at the time of casting plinth beam it is better to redesign
the plinth beam to take more load which the coloum will
carry. Note. check the mix design and use skilled manpower
while casting cubes at site. also place them in water
immediately after removing from moulds (delay in this
activity will also cause cube failure)
| Is This Answer Correct ? | 6 Yes | 0 No |
Post New Answer View All Answers
may i know the detailed description of cutting length
a rectangle grill of length 72 inch x 20 inch width.how to calculate bar spacing ,bar consist 8 mm thickness and spacing of bar is 2 inch.. calculate no of bar with formula
How much qty of stone ; sand; cement in R/R stone masonry of 136 CUM
Please let me know about answer for my Question as "What is the maximum wastage allowable of HYSD Steel in any Bridge project as per Code and Code reference also ?
when it is noted "JAMB SIM" what is the term "SIM" and what does it mean?
hi, i am doing my B.tech third year and i want to have a job in Genpact...So can you help me which kind of job would be more appropriate for me in such a company and How should i prepare for an interview?
How to find coloumn vertical cut length floor to floor & lap + bend or anything plz clearfiy
what is pile and deam foundation
how to calculate MR 9(derivation)
Kindly post me previous year interview questions with answer for post of Manager (civil engg.) for NTPC, IOC , GAIL etc. I have interview on july 2013.I will be very grateful to you. Please guide me.
How many Sft of Level Plaster per Kg
what is the list of building construction equipment & teir output?
How much for the BRC lapping in full yield and half yield < and which table to get it ?
how ratio is calculated for any grade of concrete. for e.g. sppose M20 requires(x;y:z) quantity of cememt sand and aggregate.
16 questions out of 55 were from the book GUPTA N GUPTA OBJECTIVE of civil engineering. Total ques were 4 ques from hydraullics, 7 from BMC, 4 FROM SOM, 4 from soil mechanics, 6 from transportation, 5 from engineering drawing.