1. if only 1 slab of a floor get sagged, how could be it
repaired?
2. if any footing gives the cube result, after 28 days less
than 16 n/mm2 in spite of 20 n/mm2 what are the remedies ?
Answer Posted / venu gopal
2 reasons for saging.1) bad staging/supports. 2) bad
design. any hw if it sagged it does noteffect the next slab
casting we can cast the next one. as far as repairing of
1st slab is consern we should have a graphical
representation of sag and find out the lowest level and
highest level plot them and with the help of this date we
can fix the floor level ilttle elevated than planned and
the sagged area should be concreted (screed concret) with
good mix as per site condition.
2.if it is a big footing we cannot remove and redo. so
remove the top 200mm concret by chiping and use proper
bonding agents and introduce few more rebars through the
coloun and anchor them to the old footing and change the
shape of the footing to a triangular shape with rebars and
re concrete the top surface and additional care to be taken
at the time of casting plinth beam it is better to redesign
the plinth beam to take more load which the coloum will
carry. Note. check the mix design and use skilled manpower
while casting cubes at site. also place them in water
immediately after removing from moulds (delay in this
activity will also cause cube failure)
| Is This Answer Correct ? | 6 Yes | 0 No |
Post New Answer View All Answers
how can we calculate steel value, depending on load
how to calculate cut length of re-bar in a circle . because we not place same length of re-bar in whole circle maximum in center and minimum at corner so how to calculate middle bars???
a solid steel rod length 2m dia and 20mm vertically hangs from celling and has a collar firmly atteched to it. above the collar an annular rubber washer of 40mm th. having stifness k = 5n/mm is placed. determine maximum stress in the rod caused by mass of 5 kg falling through a height of 1.2m.
What is the Systematic Responsibility Site Engineer? Who are the above and under co-oridinating ? What is office & Site co-ordination of Site Engineer?
Which ratio use for cement selery???
Analyze the rate for 1st class brick work in superstructure with 1:6 cement sand mortar. Consider 1000 cu.ft quantity and work out the rate per cu.ft
Which architectural movement is also known as jazz moderna?
Dear sir, i want to NBCC & NTPC previous exam papers email Id : madhu_bingi@yahoo.co.in
how to calculate the chair reinforcement length in slabs, footing or anywhere??
Design an underground tank of internal dimensions 6m x 3m x 3m. The soil surrounding the tank always remains dry. The tank shall be provided with a roof slab. The soil weighs 16000 N/m3 having an angle of repose of 30.
how much st. steel is required for staging of concourse slab of a elevated metro station allowing through traffic .
WHERE CAN I GET THE PREVIOUS QUESTION PAPERS OF APGENCO FOR THE THE POST OF Tr.ASSISTANT ENGINEER(CIVIL)
Laying bitumen concrete 40mm thick using 0.1372 cum of 13.2 10mm metal ,0.2387 cum of 10 5mm metal...what did it means please explain me how much cum of 10 mm metal need?
How much 1 cum of M15, M20 & M25 concrete weigh?
Explain what is 1/8 on the architect ruler denotes?