Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete
by explaining all formulas involved.
Answer Posted / kumar biswajit sinha
i think the dimension what ever is given in the question is not full , because the formula is =
V = [L X B X d] + h / 3 [ A1 + A2 + ROUTE UNDER A1 A2 ]
where ,
l = length , b = breadth , d = bottom depth , h = D - d ,
A1 = bottom area , A2= top area .
so , how can we calculate ,[ A2 ] top area without dimension .
| Is This Answer Correct ? | 501 Yes | 74 No |
Post New Answer View All Answers
In an aggregate blending plant, water is sprayed before blending is performed. If the fine content in aggregate is as high as 25 %, will not the fines form into lumps / balls and distribution will not be uniform ? Further, the fines will stick onto the interior of pug mill and its content will be low. The mixed material is stockpiled for weeks / months before use. Will it not be better that blending is done in dry condition, and water will be added only during compaction at site. Please forward your comments and suggestions.
Define What is the force exerted by the Tacoma narrows bridge?
when it is noted "JAMB SIM" what is the term "SIM" and what does it mean?
At one time what is the height of Lift for concreting for Bridge Piers Class B Loading and refer the code.
Explain what are the skills required to become an architect?
What is the yield of 100 litres of water and 10 kg of cement in grout mix?
how to workable concrete cube test M-25 design mix
List out some of the software used in the construction sector to estimate cost and monitoring expenses?
What is the standard specification of MOR and Water Absorption of Homogenous Ceramic Floor Tiles?
which has high compressive strength between hollow block and brick masonry?
Required amount of Steel bars, cement/ square feet for roofing of residential building upto 3rd floor.
PL.tell me about civil engineering questions with answer
manhole height is 1500 mm and width of brickwork is 230 mm dia of manhole covering is 560 mm brick masonry 1:4 horizontal length is 1500 mm and plaster 12 mm thick on both side 1:3. how to estimate the quantity of brickwork with mortar cement and sand for manhole chamber.
Explain what is 1/8 on the architect ruler denotes?
how to find the cement bags and sand requirements for the one square meter of internal,external,ceiling plastering by using the various ratios like 1:3,1:4,1:5,1:6