Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete
by explaining all formulas involved.
Answer Posted / karthikeyan
Volume = ((D+d)/2)*B*L
= ((0.5+0.15)/2)*1.7*2
= 0.325*1.7*2
= 1.105 cubic meter
| Is This Answer Correct ? | 45 Yes | 68 No |
Post New Answer View All Answers
what does the grad of cement shows (denotes)?
Can a wave happen in the middle of the ocean like in the movie poseidon 2006?
Sir, Iam Applied in rrb for the posts of Junior Engineer.I want to know about the or question previews to study well.Pl send it to shukla_varun1985@yahoo.com.
HOw much % of premium on DSR-2013 currently
How to calculate 1 brss for RCC work
50 acre of land to be reclaimed for an average height of 2.5 mt. Dredging area is 500mx200m size. what is the dredging depth required to reclaim the area?
Different sizes of Hollow blocks and its weight. Thanks.
How to find permissible diagonal tensile stress in reinforced brick work
What are the different theories of failure under static load?
In foundation design, while we do the base pressure check, we normally check if the attained pressure value is less than the GROSS BEARING CAPACITY of the soil which is the sum of net bearing capacity of soil and the overburden pressure. Actually, the overburden pressure acts against the net bearing capacity of the soil and I feel that we are actually increasing the bearing capacity value and doing the check. I feel that this is NOT right. Please clarify on this.
TO CONSTRUCT A 1800 SQFT CAPACITY UNDERGROUND WATER TANK HOW MUCH CUFT CONCRETE IS REQUIRED AND HOW MUCH REINFORCEMENT IS REQUIRED. FOR COSTING
Which are the top apps for you civil engineer?
residential buildings,mixing of concrete,structural,construction material,site handling.
What is difference between limit state and working stress method? How it is applies in building structure.
I have a slab of 20cm thickness of 20m by 4m in wich we are installing 15 tons electric panels , and we have put 4 H-shaped columns under the slab but we have done many cores in the slab which seems very normal , can you help me by telling me how to calculate the bearing capacity of the slab or give me an idea if i should increase more columns Note: load distribution area 12*1.5 m2