Answer Posted / mprajaneb
vector group testing: Assume that the terminals of the
primary windings are denoted as A, B, C in counter clock
wise direction and for secondary winding as a, b, c also in
counter clockwise direction. short circuit the terminals A
and a, and apply LT supply to the three terminals of HV
(Aa, B, C)
For Dy1 transformer: VbB = VcB and VbC grater than VcC.
For Dy11 transformer: VbC = VCc and VBb less than VcB.
For Yy0 transformer: VBb = VCc and VbC = VBc.
| Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
sir& friends i want the collection of recent quetions asked in interview of top most companies please send me on my email san.jsr@hotmail.com
According to IEC60034-14, When the vibration monitoring system required for motor Bearing. above which KW, it is required? and for what type of bearing the vibration probe is provided.
Why the arms of delta in a delta-wye power transmission system are kept constant??
what is the meaning of neutral displacement ???
Difference between shunt, PMG and AREP excitation. Which is the most reliable between PMG and AREP.
bitumar
what are pilot cells
Why i receive the GCU fault in my DG Sychronization panel . what all the factors considered for this fault .
If I bring a basic electric meter from the States and hook it up in Costa Rica in a development that has only one transformer for the 50 homes, will it still be accurate regarding the usage of kilowatt hours?
How many points does a Circuit can have?
Dear Brother can u tell the proper size selection of cable & the fault level calculation of braker, busbar etc. pls mail me at azeemk30@gmail.com
what is the diff. between x'mer , isolation x'mer & ultra-isolation x'mer ?????????????
what reason of line current and phase current in star connection and line current and phase current not equal in delta connection?
what does mean of RCT and STR in diffrential CT?
How many size of cable required for a 300m long and 30kw inductive lode