What is vector group? What is meant by DYN11?Why is it needed?
Answer Posted / sukhdev negi
Abobe two reply explained correctly "what is vector group".
The answer to the last question "why it is needed" is as
follows:-
By virtue of constrction & terminal connections of the
transformer, a phase difference between primary vector &
secondery vector occurs. We need to know the same for the
following reasons:-
1)Matching of vector group is required (to avoid
circulating current/ fault ), when 2 transformer need to be
operate parallal on a common bus/system.
2) to provide transformer differential protection correctly.
| Is This Answer Correct ? | 16 Yes | 11 No |
Post New Answer View All Answers
why industry prefer ht motor instead of lt motor.
we are having 15kw and 3kw motor both can run in same time , instead of using copper we are using ug aluminium cable , 35 sq.mm is suitable for its current carrying capacity..?
1.4 What is meant by CT knee point voltage and how would you determine it
we are having 110 Kv,250mA Electrostatic precipitators for coal fired boilers. what will be static voltage and current after discharge and what time it will remain before earthing?
Explain Need of a starter in a dc motor.? Also explain any two starting and speed control method of dc motor?
What will be the fault current of any system when its generation is 10% of BASE generation( FUll Load )?Will is 10% or the same as full base calculation?
Testing procedure of DG alternator stability test
Air circuit breaker safety
Q.1:What protection will be used on HT and LT side of 33/0.4 KV, MVA transformer. Indicate capacities of protective device to be used. Q.2:Which types of back-up protections are used in the power transformers? What do you understand by the term over travel in the relay? Q.3:How star and delta connected winding transformer are provided from earth fault
Showing results for capital, machinery, stock,wages, carriage in words, salaries, factory rent, repairs, fuel and power, buildings, debtors, sales, purchases, creditors, return outwords, return inwords, drawings, discount allowed, discount receivable, office expenses, bills payable, bills receivable, cash in hand, cash at bank, office rent comes under debit or credit
I AM FROM ELECTRICAL ENGINEERING ? I AM ASPIRING FOR "BHEL".HOW I HAVE TO PREPARE .ON WHICH TOPICS TO BE CONCENTRATE MORE.PLEASE GIVE FULL DETAILS OF WRITTEN EXAM.
What is fault clearing time for Current Limiting Moulded Case Circuit Breaker?.
for 4 MVA , 33K.V/6.6K.V transformer. secondary side the connected load is 3000H.P. What is the rating of capacitor bank to be insttaled.
when it is possible kvrah lead & fundamental kwh be equal in electonic trivector meters (3 ph)
internally connection of photvoltic module