what is the difference between power and distribution
transformer?
Answer Posted / shvetang dave
Power Transformer are used for step up purpose from
trnasmission station to distribution station. Normally from
750 KV to 11 KV it is to be used. It is design for only I2R
losses b'coz Iron losses are constant b'coz it is operated
for constant application.
Whereas distribution Transformers are used for step down
purposes b'cos it is used for distribution purposes. It can
be used for Factory's required power as well as in society
it can be used for home's use. It can be used for 11 kv to
230 Voltage purposes. It can be Design for iron losses
b'coz It is operated for 70 to 80% operation so I2R losses
are not so much important
| Is This Answer Correct ? | 7 Yes | 4 No |
Post New Answer View All Answers
What are books to be referred for KPTCL exam?
Why the field rheostat is adjusted such that the voltmeter reads 380V
I have a reading off 1.5ohms at my mem my main c/b is rated at 40/6 amps in a domestic house and i was told to change it to a b curve c/b is this ok
EXPLAIN THE WORKING OF SERIES REACTOR IN HT CAPACITOR BANKS (FOR VOLTAGES & CURRENTS)
explain which quantities change in the starting and the and the running condition in induction motor
my UPS suddenly goes off and all panel light also blow off.This happens even main electric supply is not interrupted.After some time it automatically starts functioning normally.Batteries are new.
how to produsing geretor power
What is warm / cold start of HT motors. How many warm start & cold start are possible in a day?
Hi Friend I am used multimeter to measure the voltage between R Phase(SS1) to R Phase(SS2). In SS1 is connected with UPS loads. But I am getting voltage between these 2 R Phases. Please give some idea friend
WHY CBCT USE ONLY IN Y PHASE NOT OTHER PHASES
What is core CT & it's function?
why should the primary of transformer be connected in delta in a heat run test?
How cable from Kit-Kat to main switch, from starter to motor are designed?
What is the tests required for a 132 kV, 400 kV , 765 kV for a Circuit Breaker and Power Transformer before commissioning ?
sir i had plane to do some project with the base of hopkinson test in AC supply its possible