WHAT IS THE %WASTAGES OF CEMENT, BRICK,TILES, STEEL,IN 1
M3,10M2,1 TON RESPECTIVELY
Answer Posted / navin baranwal
The permissible wastage for cement is 1%.For bricks
2.5%,For tiles, actually depends on the pattern laid but
taken 3-4% in general and for steel it is 3%.
Is This Answer Correct ? | 44 Yes | 14 No |
Post New Answer View All Answers
crank types
What is an object snap mode?
1.what type of the rock is most suitable for wet mix macadam in construction of road? 2.what is the highest maximum dry density and optimum moisture content can be acheive by using most suitable crush rock?
how much brick, cement, and sand required in 1mtr X 0.23mtr X 1mtr brickwork(1:4), 230mm thick wall and 10mm thick mortar , brick size 230mm X 70mm X 110mm
how to frame the sentence in voucher pad ? Description : 1.Food Expenses during site visit 2.Stamp Paper approval expenses 3.Travelling expenses 4. sweet distribution
what course did you consider thinking before you enrolled in college?
What are the uses of layer?
what is the use in canals of longitudinal drains and cross drains in lining areas?
What is the use of mirror command?
How to Calculate Materials Required for PCC 1:4:8 for 1Cum & Brickwork 1:4 for 1Cum & Plastering 1:4 (15mm Thick) for 100Sqm & RCC 1:4:8 & 2mt ( L1=1mt & L2=1mt ) length of 12mm Steel bended in 90degrees what is the formula to calculate Weight & Actual Length ?
qty. of cement & sand required (100sq.mtr) for fixing of floor and wall tiles also fixing of marble stone on the floor
how to do cementicious paint for rcc walls of cw pump house
in design case of structural member best suitrable percentage of steel limit is what
how to identify np3 pipe and np4 pipe
what is mc arther pile?