In footing (mat) if two different dia of rods are to be used
which rod should be placed at top and bottom ( eg. 10mm &
16mm dia rods)
Answer Posted / gurmeet
it will be smaller dia bars which will be placed at bottom
because the bottom part will be under compression and the
upper part will be under tension. This is because the base
preassure is acting from downward direction.
| Is This Answer Correct ? | 6 Yes | 25 No |
Post New Answer View All Answers
Describe the various methods of concrete curing?
whou haat goals do you have in your career
What is thumb rule in quantity and cost estimation of a residential building?
For 1 bag cement how i will calculate sand and metal aggregate;Here the mix proportion is 1:2.49:2.38
what are the changes in concrete pour height as per IS 456, 2009?
Technical Question of Civil Engineering
how is the reinforcement is distributed in triangular slab
Which brick is best for construction ,either fly ash or AAC BLOCKS
I want to know about rolling margin of steel :- For eg. If 2nos. bundle of 8mm dia steel with17 rods each of length 12m comes to store. During testing of 1m rod of each bundle it was found that 1rod has weight .405kg/m while other has .385kg/m. Now what will happen in case of steel payment and measurement payment ? Regards,
What year was the keystone power plant in Indiana County constructed?
beam length 73 feet 4 inch,width 01 feet,height 50 inch so every beam load how much? and what quantity of M.S ROD? both side ony two column in middle no column.pls inform me that this is stable or not ? and how much risk of this beam?
What are the different types of foundation?
As per Kandal suggestions, we have implemented rolling starts on 140 (+/- 5) degrees and we kept 3 rollars to complete the rolling before falling 125 degrees and the Aggregate AIV is below 22. But When the DBM bed is being rolled 3rd high viabration, (Before 1 plain & low ,2 high Viabrations), the aggregate is getting sharp edge agg. projections are damaged. As the literature is said that, the VG-30 Grade having better control the temp. susceptibility than Penetration grade. if so we could not get this problem at site. But we are facing on site. let me know.
3. What are the disadvantages of your present job, things you do not like about it?
calculate the quantity of cement ,sand,bars and aggregate used for 28*4 ft with 4 inch (125mm) thick