How to calculate lap,bond and hook length for preparing bar
Bending schedule ?
Answer Posted / arun sangwan
To calculate the lap length-48*D
For calculating hook & bend -As per Is 2502,The anchorage value of the of bend shall be taken as 4*D of the bar for each 45 Degree bend and for the U type hook its always taken as 16* D.
For the bond length(Development Length)-Ld-It is calculated by the formula. and it includes all the values of the anchorages.
| Is This Answer Correct ? | 317 Yes | 77 No |
Post New Answer View All Answers
As in practice, we are deducting every 2d for 90 degree bend but from where it comes means derivation or reference of IS Code.
What is the difference between Fe 500, Fe 500 D and Fe 515.
How do you measure water flowing through 300mm diameter pipes?
How to calculate quanty of steel in four leg stirrups?
What are the common ways of demolition?
What is the software used in civil engineering?
what is kribs is supporting?
What is the Systematic Responsibility Site Engineer? Who are the above and under co-oridinating ? What is office & Site co-ordination of Site Engineer?
pls tell me about method of cutting length of ties column
How much does the leaning tower of pisa lean?
How to Know that veriation acceptable in CPWD Work Of 1:6 Cement Mortor Received Lab test report.
Why should pumping be not used in case of concreting works?
very simple or less time consuming formula for reinforcement calculation by moment
How many square meter can mason layout chb per hour
how to calculate load for a bungalow and 1column carry how much load if the size of column ,9"*15" .....or total structure load......