How to convert rainforcement calculation: Running meter to kg
Answer Posted / santosh singh
suppose ...
12mm bar of one meter length
( Qty of reinforcement is =
0.00618 x sq. of dia.in mm x length of bar )
QTY = 0.00618 X [12X12] X 1
=0.089 KG PER RUNNING METER
Is This Answer Correct ? | 63 Yes | 68 No |
Post New Answer View All Answers
how many minimum admixtures are used in water froofing structures
Material calculation of cm 1:6 for 1sqm
RR masonry rate analysis
How to build the floor to ceiling bookcase?
Normally in slabs, steel quantity is not added when you calculating concrete quantity for that slab, why it is not added ?
TELL ME THE EQUATION FOR OGEE SPILLWAY
What is semirigid connections?
Can someone please be curing period of the following according to IS codes Column beam slab brick masonry raft found. and also tell how many hours/day
WHAT IS YOUR CURRENT SALARY
how to calculate quantity of cement,sand & aggregate for u.c.r / r.r masonry in cm 1:6
Where will be the maximum bending moment in a TEE Beam?
how to check and keep control on the wastage of material at site
how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.
One plate (women civil worker lifting Plate - Satti) sand measures how many cubic feet?
how to take the quantity of block work and plastering 1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate